It's not a reality show, its a real reno

Pinaster Place is half renovation & half rebuild.



Its a re-invention of our family home, and so far, its been all on paper. Work began in October 2010, and the builders have set a cracking pace.



Well, the original 12-month completion is a few months behind, but we're so close to finishing it! (And we're going mental in the rental!)





Tuesday, March 22, 2011

Steel Structure Goes Up

It's mid-March and the crane has been working all day setting up the steel superstructure and giving a sense of actual volume to Pinaster Place..... Cool!

Upper level - Parent's Zone

Building Inspectors





Ribs for the Butterfly Roof

Tuesday, March 15, 2011

Scaffolding Up


Lots of action! The scaffolding is going up for the second story, and theres been more concrete pads and stairs poured to connect the new downstairs with the kitchen. All on schedule.